Client: Carlton Aerosystems
Location: Orchard Park, NY
Project Scope: Provided engineering study and design for a 23,000 SF ISO 8 clean room assembly area within this aerospace manufacturing facility.
-
Study criteria included ASHRAE requirements, particulate levels, pressurization gradients, and temperature and humidity stability
-
Small air-handling equipment was added to improve heating and cooling capacity
-
High-efficiency remote condensing units were added to roof
-
Placement of equipment allowed cutover and re-feed of existing ductwork distribution
-
Temperature control was interfaced to the existing DDC building management system
Results: The project was completed within budget and on schedule, with no unscheduled production interruptions in the clean room space.